Prefabricated · Modular · factory to site

Design and production of
prefabricated tanks in modular metal

Modular metal tanks: fast installation, factory quality and cost efficiency

A prefabricated tank (prefabricated / modular tank) has its main components produced in the factory, then shipped to site as panels or modules and assembled there.

Prefabricated metal tank built by Behineh Ab
Construction method
Factory prefabrication + site assembly
Types
Bolted galvanized · glass-fused · portable steel
Installation time saving
About 40 to 70 percent
Transport
Modular · truck / container
Factory production with repeatable quality
Installation time cut by 40 to 70 percent
Modular transport without oversize loads
Bolted galvanized, glass-fused and portable steel
Suited to emergency and remote projects
Can be relocated and expanded

1. Introduction — prefabricated tank fabrication

Modular metal tanks: fast installation, factory quality and cost efficiency

The rapid growth of industry, urban development and the ever-increasing need for water, fuel and chemical storage infrastructure have pushed the tank industry towards solutions in which speed of execution, guaranteed quality and flexibility in transport play a decisive role. Among these, the "prefabricated tank" (prefabricated / modular tank) has emerged as one of the most successful engineering answers to these needs.

In the prefabrication approach, the main components of the tank are produced and prepared in the controlled environment of a factory instead of being built entirely at the project site, and are then transported to site as standard parts or modules and assembled there. Moving the fabrication stage from the site to the factory brings a major change in the quality, safety and economics of the project.

Behineh Ab Engineering, focusing on the production of metal tanks (carbon steel, galvanized and stainless steel) and using factory production lines, supplies prefabricated tanks that offer high structural strength together with modular transport and fast installation.

2. What is a prefabricated tank?

Definition

A prefabricated tank is a fluid storage structure whose design, cutting, forming, initial welding and preparation of connections are carried out in the factory, and which is finally sent to the place of use as panels, plates or prefabricated modules. Unlike field-erected tanks, where all welding and assembly is done on site, in a prefabricated tank most of the fabrication work is complete before it reaches the site.

Range of products

This definition covers a wide range of products, from panel tanks built by placing standard plates side by side and bolting them together, to fully prefabricated portable steel tanks that only need to be set in place and connected to the piping.

2-1. The fundamental difference from field erection

In field erection, dimensional accuracy and weld quality depend on site conditions, the skill of the crew and uncontrollable factors such as the weather. In prefabrication, these variables are controlled in the factory, and the result is a product with repeatable, guaranteed quality.

Key indicators of prefabrication

The three main factors that determine the value of a prefabricated metal tank:

Installation time saving
40 to 70 %
Main place of fabrication
Controlled factory
Transport
Modular · container
Site assembly
Days to weeks
Execution note

Because the parts are standard, a small assembly crew with no heavy welding equipment can assemble the tank in a few days; an equivalent field-erected tank may take weeks.

3. Advantages of prefabrication

The main advantage of prefabricated tanks can be summarised in three key areas: shorter installation time, factory quality control and modular transport.

3-1. A dramatic cut in installation time

Because most of the fabrication is done before arriving on site, the time the project site is occupied is kept to a minimum. Site work is mainly limited to the foundation, placing the parts and assembly. Project execution time is cut by around 40 to 70 percent compared with field erection. Work can run in parallel: while the foundation is being built on site, the tank is being fabricated in the factory. Operation starts sooner and the investment pays back faster.

3-2. Factory quality control

Welding with automatic and semi-automatic machines of uniform quality. Non-destructive testing (NDT) such as radiography, ultrasonic testing and leak testing under controlled conditions. Protective coatings (hot-dip galvanizing, epoxy, industrial paint) applied in a suitable environment without the effect of site humidity and dust. Precise control of dimensions, plate thickness and joint tolerances according to the engineering drawings.

3-3. Modular transport

Transport with an ordinary fleet without escort traffic or oversize-load permits. The tank can be delivered to remote and hard-to-reach areas and to projects beyond the reach of heavy cranes. Lower transport cost and compact packing of the panel parts.

3-4. Other advantages

Greater safety by reducing high-risk operations on site (welding at height, work in confined spaces). Relocation and expansion: many prefabricated tanks can be dismantled, reassembled and increased in capacity. Less waste and environmental impact at the project site.

4. Types of prefabricated metal tanks

Although FRP panel tanks are also on the market, Behineh Ab Engineering focuses on metal tanks, which offer greater structural strength, longer life and higher mechanical resistance.

4-1. Bolted galvanized panel tank

Hot-dip galvanized or coated steel panels are pressed, punched and prepared in the factory and joined on site with bolts and sealing washers. High corrosion resistance thanks to the zinc coating. Capacity can be increased by adding a row of panels. Suitable for drinking water, fire fighting, irrigation and wastewater. No welding needed on site.

4-2. Epoxy-coated / glass-fused panel tank

Steel panels with coatings such as glass fused to steel (glass-fused-to-steel) or industrial epoxy. Suitable for more corrosive fluids and long-life projects.

4-3. Portable steel tank

Fully prefabricated stainless steel or carbon steel tanks in one piece or several sections. Hygienic and suitable for the food, pharmaceutical and drinking water industries (304 and 316). Quick relocation between sites; ideal for temporary and emergency projects.

4-4. Technical comparison of the types
FeatureBolted galvanizedGlass-fused panelPortable steel
Main materialGalvanized steelSteel + glass coatingStainless/carbon steel
Corrosion resistanceGoodExcellentExcellent
Installation speedVery highHighImmediate
Can be relocatedYesYesVery easily
Typical useWater and fire fightingWastewater and industrialFood/emergency

5. The assembly process on site

Assembly is carried out step by step, based on the factory's standard instructions:

1. Preparation and construction of the foundation

A level, strong concrete base built for the design load; this can be done at the same time as the parts are made in the factory.

2. Placing the base and floor parts

Laying the floor plates or base ring on the foundation and levelling them precisely.

3. Assembling the panels row by row

Installing the panels row by row from bottom to top and tightening the bolts to a controlled torque.

4. Sealing the joints

Placing gaskets and special sealants between the panels to ensure there are no leaks.

5. Installing the roof, ladder and accessories

Fitting the roof, inspection hatch, inlet/outlet nozzles, overflow and instrumentation.

6. Final coating and touch-up

If needed, repairing the coating at the joints.

7. Tightness test and commissioning

Filling the tank, carrying out the leak test (hydrostatic test) and handing it over to the operator.

6. Use in emergency projects and remote areas

Modular transport and fast installation make prefabricated metal tanks an unrivalled option in special conditions.

6-1. Emergency and crisis projects

Supplying drinking water to earthquake- and flood-hit areas in the shortest possible time. Temporary fire water tanks for fighting fires in critical situations. Fast storage of fuel and water in relief operations and temporary camps.

6-2. Remote and hard-to-reach areas

Mining, oil and gas projects in desert and mountain areas where access for heavy cranes is difficult. Villages and areas without infrastructure, where field erection and a skilled welding crew are not available. Islands and coastal areas, where shipping modular parts is cheaper than moving fabrication equipment.

7. Economic comparison with field erection

The economic assessment should go beyond the initial price and be based on the total cost of ownership and of the project.

IndicatorPrefabricated tankField erection
Project execution timeShort (days/weeks)Long (weeks/months)
Site labour costLowHigh
Quality and repeatabilityHigh and guaranteedDepends on the site
Transport costMedium (modular)Low (raw materials)
Can be relocatedYesNo
Suitability for remote areasVery suitableDifficult/costly
Total cost of ownership (TCO)OptimalHigher in most cases
Economic conclusion

Although the cost of transporting the modules may be slightly higher, the shorter execution time, smaller site workforce and guaranteed quality mean that the total project cost of prefabricated tanks is lower in most situations and the investment pays back faster.

8. Conclusion

Prefabricated metal tanks offer a combination of speed, quality and flexibility that meets the needs of today's industry. Factory quality control, a dramatic cut in installation time and modular transport make these tanks a better option than field erection, especially in emergency projects and remote areas.

Relying on its ability to produce galvanized, coated and stainless steel metal tanks, Behineh Ab Engineering is ready to design, fabricate and assemble all kinds of prefabricated tanks to suit clients' needs, and can provide integrated services from consultation and design through factory production to final assembly on site.

Behineh Ab Engineering — our speciality is industrial metal tank fabrication

Technical specifications

Construction method
Factory prefabrication + site assembly
Types
Bolted galvanized · glass-fused · portable steel
Installation time saving
About 40 to 70 percent
Transport
Modular · truck / container
Uses
Water, fire fighting, industrial, emergency

Applications and industries

Drinking water and fire water storage
Drinking water and fire water storage
Remote mining and oil and gas projects
Remote mining and oil and gas projects
Earthquake-hit areas and relief operations
Earthquake-hit areas and relief operations
Food and pharmaceutical industries
Food and pharmaceutical industries (portable steel)
Villages and areas without welding crews
Villages and areas without welding crews
Temporary sites that need relocation
Temporary sites that need relocation

Frequently asked questions

Request a quote
Prefabricated tank fabrication

Enter the pressure, temperature and fluid; our engineers send a technical proposal and price within 24 working hours.

  • Written technical reply with a proposed concept drawing
  • Site visit in Tehran and surroundings
  • 24-month warranty on fabrication and welding
Call our engineering office
+98 21 4686 6276

Your details are confidential and used only to prepare a technical proposal.

All articles
  • Assembling the shell and head of a steel tank in the Behineh Ab tank fabrication workshop

    Steel Tank Manufacturing Steps, from Order to Delivery

    The steps of building a steel tank, from the data sheet to testing and dispatch. A 20,000-litre tank takes about three weeks; here is what that time is spent on.

    Read more
  • Inspector carrying out a non-destructive test on a steel tank shell weld

    Tank Tests: What Defect Does Each Test Find?

    Hydrotest, radiography, ultrasonic, liquid penetrant, magnetic particle and vacuum box. Each finds a particular defect and none can replace another. Here we compare them.

    Read more
  • Pressure vessel under hydrostatic test with a pressure gauge in the Behineh Ab workshop

    Tank Hydrostatic Test, Step by Step

    The hydrotest is a tank's final exam before delivery, and we carry it out in our own factory. The test pressure, the work before filling, and the mistake that can ruin a tank while it is being drained.

    Read more
  • Radiography film of a tank shell weld on a film viewer

    Weld Radiography: What Percentage of Seams Must Be Tested?

    The radiography percentage sets the joint efficiency, and the joint efficiency sets the plate thickness. In other words, this decision directly affects the tank's weight and price.

    Read more